Map / Model labs

OpenAI

Makes ChatGPT; closed a $122B round of committed capital in March 2026 ($110B of it announced in February); buys compute and chips from Microsoft, Oracle, Amazon, CoreWeave, AMD and Cerebras.

InterfaceCompute

Chokepoints it holds

Depends on

Supplies

AI money

Private; no public financial statements. 2025 figures come from leaked audited statements verified by the FT (reported June 2026). Projections come from investor documents reported by The Information (Feb 2026), CNBC/Reuters (Feb 2026) and the FT (Sept 2026). OpenAI reportedly filed a confidential draft S-1 on June 8, 2026 (secondary source); it has said it will not list in 2026.

AI revenue

WhatAmountPeriodDetail and source
Revenue$13.1BFY2025Audited figure via leaked statements. Techstrong.ai, 2026-06-17
Revenue$5.7BQ1 2026The Information, as cited by Techstrong. Techstrong.ai, 2026-06-17
Annualized revenue run-rate$50Bearly Oct 2026About $50B per people familiar (FT/Bloomberg), lower than the 'nearly $70B' reported in September. The FT ties the gap partly to how sales through cloud providers are counted when investors compare OpenAI to Anthropic. Bloomberg News, 2026-10-08
Annualized revenue run-rate (alternative report)$70Blate Sept 2026'Nearing $70B', up more than 70% since the start of Q3 (Reuters). OpenAI says it expects $70B by end-2026. DealStreetAsia / Reuters, 2026-09-30
Revenue projection$36BFY2026Per a company presentation (FT, Sept 2026). The Information's Feb 2026 figure was $30B. The Star / Reuters, 2026-09-19
Revenue projection$350B2030FT, Sept 2026. Cumulative 2026-2030 revenue projected at $840B. CNBC in Feb 2026 reported 'more than $280B' for 2030. The Star / Reuters, 2026-09-19
Business vs consumer splitamount not disclosedMar 2026Enterprise was 40% of revenue (up from 30% a year earlier); OpenAI expects parity with consumer by end-2026. Over 50 million paying subscribers; ads over $0.1B annual run-rate (company-reported). 2030 plan per The Information: consumer about $150B, ChatGPT Enterprise/business $70B, API $47.5B, devices $15B. SiliconANGLE, 2026-03-31

Where the money comes from

WhatAmountPeriodDetail and source
Revenue$13.1BFY2025Up 253% from $3.7B in 2024. Monthly revenue neared $2B by year-end. Techstrong.ai, 2026-06-17
Investment from a partner from Amazon (AWS)$15BFeb 2026Up-front part of Amazon's $50B commitment in the $110B round. Included in the $122B round below; do not add the two. Yahoo Finance / Reuters, 2026-02-27
Investment from a partner from Amazon (AWS)$35BFeb 2026; paid by Q3 2026Second part of Amazon's $50B, originally conditional. Amazon's filing shows $13.7B paid in April to June 2026 and $21.3B after June 30. Included in the $122B round below; do not add the two. Amazon via SEC EDGAR, 2026-07-31
Investment from a partner from Nvidia$30BFeb 2026Part of the $110B round. CNBC reported it is not tied to deployment milestones; unclear whether it replaces the Sept 2025 'up to $100B' letter of intent. Included in the $122B round below; do not add the two. Yahoo Finance / Reuters, 2026-02-27
New shares sold from SoftBank$30BFeb 2026SoftBank's share of the $110B round; payment schedule not given in the source. Included in the $122B round below; do not add the two. Yahoo Finance / Reuters, 2026-02-27
New shares sold from softbank, amazon, nvidia, microsoft, mgx, venture-funds and others$122Bclosed Mar 31, 2026Final round size: $122B 'committed capital' at an $852B post-money valuation (up from the $110B announced). Led by SoftBank; also a16z, D.E. Shaw, MGX, TPG, T. Rowe Price, Amazon, Nvidia, Microsoft, and almost $3B from individuals via banks. Includes the Amazon, Nvidia and SoftBank amounts above; source does not say which parts are tranched. SiliconANGLE, 2026-03-31
Bank loans from Banks$4.7Bas of Mar 2026Revolving credit line expanded to about $4.7B; undrawn at the time. SiliconANGLE, 2026-03-31
Supplier financing from Nvidiaup to $250Btalks reported July 2026Superseded. Reported in July 2026 as talks on a 10 GW southern Ohio campus developed by a SoftBank energy unit and leased by OpenAI. On August 17, 2026 Nvidia signed guarantees capped at $105B for about 4.25 GW at SB Energy's PORTS-Pike campus in Pike County, Ohio, which appears to be the same project. Kept for the record; not counted anywhere. The Next Web, 2026-07-27
New shares sold from softbank-mgx-potentialup to $30Bin talks, Sept-Oct 2026Sought 'at least' $30B at about $1.4T in September to October 2026; cut to about $20B at $1.25T on October 30. About $11B was reported wired by November 6 (Bloomberg, unnamed sources; Reuters also reported the close, citing its own source); OpenAI has not confirmed it, and the rest may close in the following weeks. Dealroom, 2026-10-20
New shares sold from investors not named$11Breported wired by Nov 6, 2026Reported first close of the round at a $1.25T valuation, citing unnamed sources; the round could reach about $20B in total (Bloomberg, via Reuters). Reuters separately reported the close from its own source. Not confirmed by OpenAI. Reuters via GV Wire, 2026-11-06

Where it goes

WhatAmountPeriodDetail and source
Research and development$19.2BFY2025Includes $10.59B paid to Microsoft (mostly computing). Cost of revenue was a further $7.5B and sales and marketing $5.73B. Operating loss was $20.92B. Techstrong.ai, 2026-06-17
Other$8BFY2025Approximate cash burn in 2025 after excluding non-cash items, stock pay and Microsoft computing credits (unnamed sources). Techstrong.ai, 2026-06-17
Other$3.7BQ1 2026Reported cash burn in Q1 2026 (The Information), on revenue of $5.7B. Techstrong.ai, 2026-06-17
Renting computeup to $856B2026-2030 projectionCompute and infrastructure spending in a July 2026 investor presentation (FT). In February OpenAI had told investors about $600B through 2030; categories may not match exactly. The Next Web, 2026-09-19
Renting computeup to $600Bthrough 2030 (Feb 2026 projection)Reset from Altman's earlier '$1.4 trillion for 30 GW' talk. Yahoo Finance / Reuters, 2026-02-20

Spending it has promised

WhatAmountPeriodDetail and source
Headline compute commitments with multipleup to $1.4Tabout 8 years (stated late 2025)Mix of signed contracts and letters of intent; later reset to about $600B through 2030 (Feb 2026) and then $856B of compute and infrastructure spending 2026-2030 in a July 2026 presentation. Fortune, 2025-11-12
Oracle cloud capacity with Oracle$300Babout 5 years starting 2027Reported by the WSJ; tied to the 4.5 GW Stargate capacity deal. Reported contract, not confirmed in a filing opened here. DatacenterDynamics, 2025-09
AWS cloud capacity (original deal) with Amazon (AWS)$38Bmulti-year from Nov 2025Nvidia GB200/GB300 capacity. GeekWire, 2026-02-27
AWS cloud capacity (Feb 2026 expansion) with Amazon (AWS)$100B8 yearsAdded alongside Amazon's $50B investment; includes 2 GW of Trainium capacity. GeekWire, 2026-02-27
Cerebras compute with Cerebras$10B2026-2028'Over' $10B for 750 MW, per reports citing people familiar. A May 2026 report put the deal at over $20B; the ledger uses that figure as an 'up to' row. Storyboard18, 2026-01-15
Nvidia systems letter of intent with Nvidiaamount not disclosedfrom H2 2026At least 10 GW of Nvidia systems, with Nvidia investing 'up to $100B' as capacity came online. Still only a letter of intent as of Dec 2025; reported shelved in favor of the $30B direct stake. DatacenterDynamics, 2026-02
Microsoft Azure with Microsoft$10.6BFY2025 (paid)Amount OpenAI paid Microsoft in 2025 within R&D. The multi-year commitment is the $250B Azure row. Techstrong.ai, 2026-06-17
Microsoft Azure (incremental commitment) with Microsoft$250Bterm not disclosedAgreed in OpenAI's October 2025 restructuring. Microsoft booked $10.0B of revenue from OpenAI in July to September 2026 and was owed $7.2B at September 30. The Register, 2026-01-29

Who it depends on for revenue

Money flows with other companies

Money fromMoney toTypeAmountWhat, and source
OpenAIOracleCompute contract$300BOracle cloud capacity (Stargate 4.5 GW) about 5 years from 2027 DatacenterDynamics, 2025-09
OpenAIMicrosoftCompute contract$250BIncremental commitment by OpenAI to buy $250B of Azure cloud services, agreed during OpenAI's restructuring in fall 2025. By January 2026, 45% of Microsoft's $625B commercial backlog was directly attributable to OpenAI. multi-year (term not stated in source) The Register, 2026-01-29
OpenAIAmazon (AWS)Compute contract$100BAWS expansion incl. 2 GW of Trainium 8 years GeekWire, 2026-02-27
OpenAIAmazon (AWS)Compute contract$38BAWS capacity on Nvidia GB200/GB300 multi-year GeekWire, 2026-02-27
Amazon (AWS)OpenAIEquity investment$35BLoop Second part of Amazon's $50B: $13.7B paid April to June 2026 and the remaining $21.3B after June 30, per Amazon's filing Amazon invests in the lab; the lab commits to spend on AWS. when conditions met (reported completed July 2026) Amazon via SEC EDGAR, 2026-07-31
NvidiaOpenAIEquity investment$30BLoop Nvidia's $30B in OpenAI's $110B round at a $730B pre-money valuation (round closed Mar 31, 2026 at $122B committed, $852B post-money). Funding schedule not disclosed. OpenAI committed in the same announcement to 3 GW of inference capacity and 2 GW of training on Nvidia Vera Rubin systems, so much of the money is expected to come back to Nvidia as chip purchases. one-time (funding round) OpenAI, 2026-02-27
SoftBankOpenAIEquity investment$30BSoftBank's first $30B in OpenAI (April and December 2025) April to December 2025 TechInformed, 2026-01-07
SoftBankOpenAIEquity investment$30BSoftBank's 2026 OpenAI investment, part of the $122B round at an $852B valuation. SoftBank reports a cumulative $64.6B for about 13%; that is $4.6B more than the two rows here, and our sources do not itemize the difference. 2026, three $10B tranches Reuters via The Star, 2026-10-01
OpenAIMicrosoftRevenue share$24.1BRevenue Microsoft recorded from commercial arrangements with OpenAI (Azure plus revenue share) in fiscal 2026; ~$10B more in July–Sept 2026 (secondary). FY2026 Microsoft via SEC EDGAR, 2026-10-28
OpenAICoreWeaveCompute contractup to $22.4BThree OpenAI compute contracts, each 'up to' ($11.9B + $4B + $6.5B) multi-year from 2025 CoreWeave (press release), 2025-09-25
OpenAICerebrasCompute contractup to $20B750 MW Cerebras compute for OpenAI, reported as 'over $20B' multi-year Yahoo Finance, 2026-05-14
OpenAIStargate JVEquity investmentup to $19BReported initial equity commitment to the Stargate JV. Initial commitment Wikipedia (citing The Information), 2025-01-23
Amazon (AWS)OpenAIEquity investment$15BLoop Up-front part of Amazon's $50B OpenAI expanded its AWS commitment by $100B over 8 years at the same time. 2026 GeekWire, 2026-02-27
MicrosoftOpenAIEquity investment$13BLoop Microsoft's total funding commitment to OpenAI; $11.9B funded by June 30, 2026, for an approximate 25% stake on an as-converted basis OpenAI spends heavily on Azure ($250B incremental commitment) and pays Microsoft a revenue share, so Microsoft's investment returns to it as revenue. cumulative Microsoft via SEC EDGAR, 2026-10-28
AMDOpenAIEquity investmentamount not disclosedLoop Warrant for up to 160 million AMD shares at $0.01, vesting as OpenAI deploys AMD GPUs (6 GW) and AMD's stock rises (to $600 for the last tranche). AMD gives OpenAI shares that vest only as OpenAI buys AMD chips. H2 2026 to Oct 2030 The Next Platform, 2025-10-06
MGX (Abu Dhabi)OpenAIEquity investmentamount not disclosedCo-led OpenAI's $122B round. MGX's amount was not disclosed. 2026-03-31 UAE Preferred, 2026-07-02
Venture capital fundsOpenAIEquity investmentamount not disclosedAndreessen Horowitz and D. E. Shaw (co-leads), Sequoia, Thrive and others in the $122B round. VC amounts were not disclosed. About $9B to $12B of the round is not attributed to Amazon, Nvidia or SoftBank. 2026-03-31 The Next Web, 2026-03-31
OpenAIAMDChip purchaseamount not disclosed6 GW of AMD Instinct GPUs; AMD says 'tens of billions of dollars' of revenue. H2 2026 to Oct 2030 The Next Platform, 2025-10-06
OpenAIBroadcomChip purchaseamount not disclosedCustom 'Jalapeno' accelerator; no dollar value disclosed. 1.3 GW 2027, ~5 GW 2028 The Next Platform, 2026-09-10

Amounts in US dollars. "Up to" amounts are maximums or depend on conditions. See Does it add up? for the full picture.

AI power

Sites

Site and buyerPlannedStatusWhere its power comes from, and source
Stargate AbileneOpenAI with Crusoe, Abilene, Texas1.2 GWfacility (running figure is IT load)0.82 GW running Being built State policy risk all 8 buildings about Nov 2026Grid plus an on-site gas plant. Oracle confirmed about 0.62 GW of IT load running in September; Epoch estimates all eight buildings, about 0.82 GW, by November. Oracle and OpenAI dropped a planned expansion toward 2.1 GW in March 2026. Epoch AI, 2026-10-28
Stargate Shackelford CountyOpenAI with Oracle, Shackelford County, Texas1.4 GWIT load (about 2 GW at the meter)Being built State policy risk first building about Aug 2027, full late 2028On-site gas. Five of ten building shells done in September 2026; first building now expected about a year later than first planned. Epoch AI, 2026-07-31
Stargate New Mexico (Project Jupiter)OpenAI with Oracle, Doña Ana County, New Mexico1.8 GWIT loadBeing built planned late 2028; at riskOff-grid: up to 2.45 GW of Bloom fuel cells, which replaced planned gas turbines in April 2026, plus solar. On September 24, 2026, press reports said Oracle had sent a force-majeure notice to the developer, citing potential delays in securing power. Oracle said the notices did not establish a delay or change delivery expectations and that the project remained on its planned schedule. Epoch AI, 2026-07-31 Bloomberg via Bloomberg Government, 2026-09-24 TechCrunch, 2026-09-24
Stargate Milam CountyOpenAI, Milam County, Texas0.86 GWIT loadBeing built State policy risk late 2028SB Energy: mostly new solar and batteries plus grid. Epoch AI, 2026-05-22
Stargate Port Washington (Project Lighthouse)OpenAI with Oracle, Port Washington, Wisconsin0.9 GWIT load (1.3 GW at the meter)Being built delay scenario: partial power about June 2028, full about April 2029Grid, about 70% from solar, wind and batteries. A restarted review of the transmission line feeding it would push power to those dates. Epoch AI, 2026-07-24
Stargate Saline TownshipOpenAI with Oracle, Saline Township, Michigan1.4 GWfacilityBeing built 2028DTE 1.4 GW supply contract plus a 1.4 GW utility battery. Some local and environmental permits still pending. Epoch AI, 2026-04-17
Stargate LordstownOpenAI, Lordstown, Ohioup to 0.3 GWfacility, up toAnnounced State policy risk no dateNot stated. No visible construction. Epoch AI, 2026-04-17
Stargate UAEOpenAI, Abu Dhabi, UAE1 GWbasis unknownBeing built first 200 MW due 2026, not confirmed runningNot stated. A 1 GW cluster inside a 5 GW campus. Gulf News, 2025-10-16
Stargate Abilene expansionOpenAI with Oracle, Abilene, Texas0.6 GWbasis unknownCancelled State policy risk dropped March 2026 The capacity went to Microsoft through Crusoe. Tom's Hardware, 2026-03
PORTS-Pike campusOpenAI with SB Energy, Piketon, Ohio4.2 GWIT load (3.75 GW more optional)Announced State policy risk in phases from 2028At least 10 GW of new generation built by SB Energy. OpenAI is the tenant on a 20-year lease; Nvidia invests $1.5B and guarantees the campus hosts only Nvidia chips. NVIDIA (investor relations), 2026-08-17

Planned gigawatts are not all measured the same way: 5 sites report computing (IT) load, 3 report total site power, and 2 do not say. Total site power runs roughly 20 to 50 percent above computing load, so sums across sites are approximate.

Chip and cloud deals sized in gigawatts

Buyer and sellerSizeStatusWhat, and source
OpenAIfrom Oracle4.5 GWAnnounced 2026Cloud capacity across Stargate sites; overlaps the sites above. DatacenterDynamics, 2025-07
OpenAIfrom Nvidiaup to 10 GWOption or up to 2026Letter of intent only. Reports in February 2026 said Nvidia's roughly $30B investment in OpenAI replaced it; others say the two are separate. Not counted in our totals. DatacenterDynamics, 2026-02
OpenAIfrom AMD1 GWAnnounced 2026Binding commitment to buy the first 1 GW, deploying from the second half of 2026. AMD (SEC filing), 2025-10-06
OpenAIfrom AMDup to 5 GWOption or up to Further purchases up to 6 GW in all, tied to AMD share warrants; not committed. AMD (SEC filing), 2025-10-06
OpenAIfrom Broadcomup to 10 GWAnnounced 2026OpenAI-designed chips, racks deployed from late 2026 to the end of 2029; signed as a term sheet. OpenAI, 2025-10-13
OpenAIfrom Amazon (AWS)2 GWAnnounced Trainium capacity. The Decoder, 2026-04-30
OpenAIfrom Cerebras0.75 GWAnnounced 2026Through 2028. The Energy Mag, 2026

Power supply deals

Project and typePowerStatusDetail and source
On-site gas for Stargate Shackelford CountyGas turbines on site, for OpenAI2 GWBeing built 2028About 2 GW at the meter for a 1.4 GW computing load; supplier not confirmed. Epoch AI, 2026-04-17
SB Energy power for Stargate Milam CountySolar and batteries, for OpenAI1.2 GWBeing built 2028Mostly new solar and batteries for a 1.2 GW site; due late 2028. Epoch AI, 2026-04-17
Grid supply for Stargate Port WashingtonGrid supply, for OpenAI1.3 GWBeing built 20281.3 GW from the grid, about 70% from solar, wind and batteries; full power now about April 2029. Epoch AI, 2026-04-17
DTE supply for Stargate Saline TownshipGrid supply, for OpenAI1.4 GWAnnounced 2028A 19-year 1.4 GW contract plus a 1.4 GW utility battery, conditionally approved December 2025. Latitude Media, 2026-01-07

Power in gigawatts. Deals sized in gigawatts overlap with sites and are never added to them. See Is there enough power for AI? for the full picture.