Banks (JPMorgan, Goldman Sachs, MUFG, Mizuho, SMBC and others). Make the bridge loans, margin loans and construction loans that carry AI projects until bonds or private credit take them over.

Capital

Depends on

No sourced links yet.

Supplies

AI money

2025 to October 2026

Where the money comes from

Nothing sourced yet.

Where it goes

WhatAmountPeriodDetail and source
Other to Crusoe$7.1BMay 2025JPMorgan-led construction loan for phase 2 of the 1.2 GW Abilene, Texas campus (Crusoe/Blue Owl/Primary Digital JV), leased to Oracle for OpenAI. Newmark (press release via Nasdaq), 2025-05-22
Other to Oracleup to $38BSought September 2025Oracle 'sought a debt package of about $38bn' for data centers. The lenders and the final closing were not confirmed in the source we read. DatacenterDynamics (citing Financial Times), 2025-12-17

Money flows with other companies

Money fromMoney toTypeAmountWhat, and source
BanksSoftBankLoan$40BBridge loan (JPMorgan, Goldman Sachs, Mizuho, SMBC, MUFG) to fund the 2026 OpenAI investment. $10B of undrawn capacity was cancelled in October 2026. Matures March 2027 The Next Web, 2026-04-23
BanksOracleLoanup to $38BOracle reportedly sought about $38B of debt for data-center projects (September 2025); lenders not named 2025-09-30 DatacenterDynamics (citing Financial Times), 2025-12-17
BanksVantage Data CentersLoan$38B'Jacquard' project loans (JPMorgan, MUFG lead) for Stargate campuses in Texas and Wisconsin. 5-year loans Wall Street Journal via Tiger Brokers, 2025-11-11
BanksSoftBankLoan$20BMargin loan secured on SoftBank's Arm Holdings shares. Outstanding Reuters via The Star, 2026-08-04
BanksSpaceXAI (xAI)Loan$20BBridge loan refinancing X and xAI high-yield debt matures Sept 2027 The Next Web, 2026-05-21
BanksSTACK InfrastructureLoan$18BDebt (SMBC, MUFG, BNP Paribas, Goldman Sachs led; may include bonds) for an Oracle-affiliated Stargate site in New Mexico. 2025-11 Octus, 2025-11-11
BanksSoftBankLoan$11.9BSyndicated loan from about 20 banks. The source says it was arranged about a week before the September 24 bond sale, so the date is approximate. Two years European Business Magazine, 2026-09-25
BanksSoftBankLoanup to $10BMargin loan secured on SoftBank's OpenAI shares, reported as being arranged in August 2026 Two years, due August 2028 Reuters via The Star, 2026-08-06
BanksCrusoeLoan$7.1BJPMorgan-led construction loan for Abilene phase 2 (Crusoe/Blue Owl/Primary Digital $15B JV, 1.2 GW). The site is leased to Oracle and used by OpenAI. Construction loan Newmark (press release via Nasdaq), 2025-05-22
BanksCoreWeaveLoan$3.1BMorgan Stanley/MUFG-led GPU-backed loan (DDTL 5.0), SOFR+4.50% ~5.5 years CoreWeave via Business Wire, 2026-05-18
BanksCoreWeaveLoan$2.6BJPMorgan/MUFG-led loan (DDTL 5.5), SOFR+5.50% ~5 years Pulse 2.0, 2026-08-11
BanksMistralLoan$830MSeven-bank loan (BNP Paribas, Credit Agricole CIB, HSBC, MUFG and three others) to buy Nvidia chips for a Paris-area data center. not disclosed Reuters via Yahoo Finance, 2026-03-30

Amounts in US dollars. "Up to" amounts are maximums or depend on conditions. See Does it add up? for the full picture.

Data as of 2026-10-30. Cite as: Ye, Mike. "Banks" (banks). AI Lattice, dataset v0.3.0. https://ailattice.ai/e/banks/. How to cite.