Map / Model labs
Mistral
European lab; raised €3B at €21B to build 1 GW of European compute.
Depends on
- EU AI Office: General-purpose model enforcement. From Aug 2, 2026, fines up to 3% of worldwide turnover or €15M, whichever is higher. Praxikon, 2026-08 Our inference
- Banks: Seven-bank loan (BNP Paribas, Credit Agricole CIB, HSBC, MUFG and three others) to buy Nvidia chips for a Paris-area data center. Loan, $830M. Reuters via Yahoo Finance, 2026-03-30
Supplies
No sourced links yet.
AI money
Funding rounds Sept 2025 and Sept 2026, debt March 2026, revenue statements Jan-Sept 2026. Euros converted at about US$1.17 per euro, the rate implied by AFP's own conversion on 2026-02-11 (EUR 1.2B = US$1.4B); not an official reference rate. Not verified in this pass (web search limit reached).
AI revenue
| What | Amount | Period | Detail and source |
|---|---|---|---|
| Annual recurring revenue | $400M | February 2026 | Passed US$400M, up from about US$20M a year earlier; target US$1B ARR by end-2026. The Next Web, 2026-03-30 |
| 2026 revenue target | $1.2B | FY2026 target | CEO: revenue 'should cross a billion [euros] by the end of the year.' A target, not a result. In Sept 2026 Mistral still projected passing 'a billion in annual recurring revenue' by end-2026 (currency not stated). AFP via Citizen Digital, 2026-01-23 |
Where the money comes from
| What | Amount | Period | Detail and source |
|---|---|---|---|
| New shares sold from Samsung Electronics (lead); Scaleup Europe Fund (EQT); PSG Equity; Nvidia | $3.5B | Series D, 2026-09-08 | EUR 3B at more than EUR 21B post-money valuation. Led by Samsung Electronics; co-led by the EU-backed Scaleup Europe Fund (managed by EQT) and PSG Equity. Euronews says existing investor Nvidia also added to its stake. Per-investor amounts not disclosed. Called the largest equity round ever by a European tech company. Orrick (Mistral's law firm), 2026-09-08 |
| New shares sold from ASML | $2B | Series C, September 2025 | EUR 1.7B at EUR 11.7B valuation. ASML put in EUR 1.3B (about US$1.5B) for about 11%, becoming the largest shareholder. DutchNews.nl, 2025-09-09 |
| Bank loans from Banks | $830M | 2026-03-30 | First debt raise: US$830M from seven banks incl. BNP Paribas, Credit Agricole CIB, HSBC and MUFG, to buy 13,800 Nvidia chips for a data center at Bruyeres-le-Chatel near Paris. Reuters via Yahoo Finance, 2026-03-30 |
Where it goes
| What | Amount | Period | Detail and source |
|---|---|---|---|
| Buying chips to Nvidia | $830M | 2026 | 13,800 Nvidia chips funded by the March 2026 debt; exact chip spend not disclosed, the loan size is the best available proxy. Reuters via Yahoo Finance, 2026-03-30 |
| Data centers and equipment | $1.4B | announced 2026-02-11, no timeline given | EUR 1.2B for data centers in Sweden, its first outside France (AFP's conversion US$1.4B). Mistral's own statement; cost-sharing with partners not stated. AFP via Malay Mail, 2026-02-11 |
| Data centers and equipment | up to $4.7B | multi-year, end date not stated | Euronews: Mistral is 'already spending' EUR 4B on data centers in France and Europe (one site near Paris running, one under construction in Sweden). Includes the Sweden EUR 1.2B; no breakdown or timeline. Euronews, 2026-09-08 |
| Buying chips | up to $1.2B | 2026 (CEO estimate, Jan 2026) | CEO Arthur Mensch said Mistral would 'likely' spend about the same as its revenue (about EUR 1B) on AI chips and related infrastructure in 2026. AFP via Citizen Digital, 2026-01-23 |
Spending it has promised
| What | Amount | Period | Detail and source |
|---|---|---|---|
| Partner in 1.4 GW AI campus near Paris (joint venture led by MGX and Bpifrance, with Nvidia) with mgx; Bpifrance; nvidia | amount not disclosed | construction from H2 2026, operations by 2028 | Announced 2025-05-19. Capacity 'expected to ultimately' reach 1.4 GW. No investment amount and no Mistral stake disclosed. Abu Dhabi Media Office, 2025-05-19 |
| Target of 200 MW of own compute capacity across Europe | amount not disclosed | by end-2027 | Stated goal, not a contract. Reuters via Yahoo Finance, 2026-03-30 |
Who it depends on for revenue
- ASML held about 11% after Sept 2025, its largest shareholder at that time; post-Series D stakes not disclosed. DutchNews.nl, 2025-09-09
Money flows with other companies
| Money from | Money to | Type | Amount | What, and source |
|---|---|---|---|---|
| ASML | Mistral | Equity investment | $1.5B | ASML invested EUR 1.3B for about 11% of Mistral. one-time DutchNews.nl, 2025-09-09 |
| Banks | Mistral | Loan | $830M | Seven-bank loan (BNP Paribas, Credit Agricole CIB, HSBC, MUFG and three others) to buy Nvidia chips for a Paris-area data center. not disclosed Reuters via Yahoo Finance, 2026-03-30 |
| Samsung Electronics | Mistral | Equity investment | amount not disclosed | Samsung led Mistral's EUR 3B Series D (total round ~US$3.5B; Samsung's share not disclosed). one-time Orrick, 2026-09-08 |
| Nvidia | Mistral | Equity investment | amount not disclosed | Existing investor Nvidia added to its Mistral stake in the Series D; amount not disclosed. one-time Euronews, 2026-09-08 |
| Mistral | Nvidia | Chip purchase | amount not disclosed | 13,800 Nvidia chips for the Bruyeres-le-Chatel data center; price not disclosed (funded by the US$0.83B loan). 2026 Reuters via Yahoo Finance, 2026-03-30 |
Amounts in US dollars. "Up to" amounts are maximums or depend on conditions. See Does it add up? for the full picture.
Data as of 2026-11-17. Cite as: Ye, Mike. "Mistral" (mistral). AI Lattice, dataset v0.6.0. https://ailattice.ai/e/mistral/. How to cite.