AI Lattice

Map / Model labs

Meta META

Builds its own campuses and rents from Google, CoreWeave and Nebius; its Muse AI agent app reached No. 1 on the US App Store in September 2026.

InterfaceComputeEnergy

Chokepoints it holds

Depends on

Supplies

AI money

Latest quarter = Q3 2026 (July–Sept 2026, reported 2026-10-21). Nine months = Jan–Sept 2026. TTM not computed (Q4 2025 base not opened).

AI revenue

WhatAmountPeriodDetail and source
Total revenue (ad business that funds AI spend)$64.6BQ3 2026Up 26%. Meta does not report separate AI revenue. Meta Platforms via SEC EDGAR, 2026-10-21

Where the money comes from

WhatAmountPeriodDetail and source
Cash from its own business$32.8BQ3 2026Nine months 2026: $96.873B. Meta Platforms via SEC EDGAR, 2026-10-21
Bonds from Bond buyers$24.9B9 months to Sep 2026Net proceeds from long-term debt. Matches the ~$20–25B, up-to-six-part bond sale Bloomberg reported Meta was preparing on 2026-04-30. Long-term debt rose to $80.9B at Sept 30, 2026 from $58.7B at Dec 31, 2025. Meta also sold $30B of bonds in late 2025. Meta Platforms via SEC EDGAR, 2026-10-21
Off-balance-sheet vehicle from Blue Owl$27.3BOct 2025Hyperion (Louisiana) joint venture: 80% owned by Blue Owl funds, 20% by Meta; the JV (Beignet Investor) sold ~$27.3B of bonds due 2049 at 6.58% (Pimco bought $18B); Blue Owl put in about $3B of equity. Debt sits off Meta's balance sheet; Meta leases the campus in 4-year blocks and gives a residual value guarantee (pays investors if it walks away). Wall Street Journal via Tiger Brokers, 2025-11-11
Off-balance-sheet vehicle from BlackRockup to $12Breported July 2026El Paso, Texas data center: a BlackRock-backed vehicle ('Sopaipilla Investor', 80%; Meta 20%) was reportedly preparing ~$12B of bonds due 2048, backed by Meta's 20-year lease from 2028; investors wanted yields above 7%. 'Reportedly'; closing not confirmed. Stocktwits, 2026-07-24

Where it goes

WhatAmountPeriodDetail and source
Data centers and equipment$34.9BQ3 2026Includes $0.964B of finance-lease principal. Nine months 2026: $85.82B. Meta Platforms via SEC EDGAR, 2026-10-21
Data centers and equipmentup to $145BFY2026 guidanceRange $135–145B including finance-lease principal (narrowed from $130–145B). Upper end shown. Implies $49–59B in Q4 2026. Meta Platforms via SEC EDGAR, 2026-10-21
Data centers and equipmentamount not disclosedFY2027Meta expects to keep investing aggressively in 2027; budget still being set; no number given. Meta Platforms via SEC EDGAR, 2026-10-21
Investing in AI companies$2.5B9 months to Sep 2026Payments for non-marketable equity investments ($0.874B in Q3). Non-marketable equity holdings total $32.6B at Sept 30, 2026; investees not named in the release. Meta Platforms via SEC EDGAR, 2026-10-21
Buybacks and dividends$4.1B9 months to Sep 2026Dividends only ($1.361B in Q3); no share repurchases in 2026 (Q3 2025 buybacks were $3.3B). Meta Platforms via SEC EDGAR, 2026-10-21
Other$9.9B2026Legal charge tied to an agreement with US state attorneys general; included in 2026 expense guidance of $175–179B. Meta Platforms via SEC EDGAR, 2026-10-21

Spending it has promised

WhatAmountPeriodDetail and source
Hyperion lease and residual value guarantee with Blue Owlamount not disclosed~16-year guarantee; leases up to ~20 yearsMeta must make investors whole if it does not renew; guarantee size not given in sources opened. IFR, 2026

Money flows with other companies

Money fromMoney toTypeAmountWhat, and source
Bond buyersMetaBonds$30BMeta $30B bond, the largest non-acquisition high-grade bond sale ever. 2025-10-30 Reuters via Yahoo Finance, 2026-02-09
Bond buyersMetaBonds$24.9BMeta long-term debt proceeds in 2026 (consistent with the ~$25B April 2026 bond sale). 9 months to Sep 2026 Meta Platforms via SEC EDGAR, 2026-10-21
MetaCoreWeaveCompute contract$21BExpanded AI cloud capacity agreement 2026–2032 CoreWeave via Business Wire, 2026-04-09
MetaNebiusCompute contractup to $15BOptional capacity, capped at $15B; can be sold to others 5 years Nebius / SEC EDGAR, 2026-05-13
MetaCoreWeaveCompute contractup to $14.2BOriginal Meta compute contract ('up to' $14.2B) 2025–2031 The Energy Mag, 2026-02-25
BlackRockMetaBondsup to $12BReported ~$12B of bonds via BlackRock-backed 'Sopaipilla Investor' (80% owner) for Meta's El Paso data center, backed by Meta's 20-year lease from 2028. 2026-07 Stocktwits, 2026-07-24
MetaNebiusCompute contract$12BMeta dedicated compute (firm part of 'up to $27B' deal) 2027–2032 The Next Web, 2026-03-16
Hyperion JV (Meta, Blue Owl)MetaAcquisition$3BOne-time distribution of about $3B to Meta for contributing the land and construction in progress (Blue Owl effectively bought 80% of the project). 2025-10-21 Meta, 2025-10-21
MetaNebiusCompute contract$3BFirst Meta contract 5 years The Next Web, 2026-03-16
AMDMetaEquity investmentamount not disclosedLoop Warrant for up to 160 million AMD shares, vesting on installed-technology and share-price milestones. AMD gives Meta shares that vest as Meta buys AMD chips. through 2030 The Next Platform, 2026-02-24
MetaAMDChip purchaseamount not disclosed6 GW of AMD GPUs over five years; first 1 GW from H2 2026, rest contracted successively through 2030. H2 2026 to 2030 The Next Platform, 2026-02-24
MetaConstellation EnergyPower contractamount not disclosed20-year PPA for 1,121 MW from Clinton nuclear plant; value not disclosed. June 2027-2047 Business Wire (Constellation press release), 2025-06-03
MetaEntergyPower contractamount not disclosedMeta's tariff payments and contributions to cover the cost of seven new gas units (5.2+ GW) plus grid work in Louisiana, tied to $15B of Entergy capital spending; plus ~$2B of customer benefits. Total payments not disclosed. multi-decade Utility Dive, 2026-04-30
MetaHyperion JV (Meta, Blue Owl)Lease or guaranteeamount not disclosedMeta leases Hyperion from the JV and guarantees investors are repaid if it leaves. 4-year renewable lease blocks, ~16-year residual value guarantee IFR, 2026
MetaHyperion JV (Meta, Blue Owl)Lease or guaranteeamount not disclosedMeta rents the campus and guarantees its residual value (a capped cash payment if it walks away). Leases with a four-year initial term. Value guarantee covers the first 16 years Meta, 2025-10-21
MetaOkloPrepaymentamount not disclosedMeta prepays for power from a planned 1.2 GW Oklo campus in Ohio; funds go to nuclear fuel. Amount not disclosed. as early as 2030 Orrick (deal counsel news), 2026-01-13
MetaTerraPowerPrepaymentamount not disclosedMeta funds development of two Natrium units with rights to up to six more (2.8 GW total). Amount and form undisclosed. by 2035 American Nuclear Society (Nuclear News), 2026-01-12
MetaVistraPower contractamount not disclosedMeta-supported uprates of about 433 MW at three Vistra nuclear plants; value not disclosed early 2030s onward American Nuclear Society (Nuclear News), 2026-01-12

Amounts in US dollars. "Up to" amounts are maximums or depend on conditions. See Does it add up? for the full picture.

AI power

Sites

Site and buyerPlannedStatusWhere its power comes from, and source
Meta HyperionMeta, Richland Parish, Louisiana5 GWbasis unknownBeing built 2 GW by 2030; 5 GW about 2032Entergy gas plants: 2.25 GW approved, about 5.25 GW more awaiting state approval; plus solar. Nothing running yet. Meta moved 80% of the campus to a Blue Owl vehicle. Global Data Center Hub, 2026-07-20
Meta PrometheusMeta, New Albany, Ohio1 GWIT load0.47 GW running Being built State policy risk about 1 GW by mid-2028Grid plus off-grid gas (Williams 'Socrates' plants). Includes tent-style buildings. Epoch AI, 2026-10-02
Meta El PasoMeta, El Paso, Texas1 GWbasis unknownBeing built State policy risk from 2028366 MW of modular gas generators awaiting a state vote. BlackRock funds own 80%. W.Media, 2026-07-28

Planned gigawatts are not all measured the same way: 1 sites report computing (IT) load, 0 report total site power, and 2 do not say. Total site power runs roughly 20 to 50 percent above computing load, so sums across sites are approximate.

Power supply deals

Project and typePowerStatusDetail and source
Three Entergy gas plants for Meta's HyperionGas plant built for the campus, for Meta2.2 GWBeing built 2029Approved by Louisiana regulators in August 2025; due mid to late 2029. Industrial Info Resources, 2025-08
Seven more Entergy gas plants for HyperionGas plant built for the campus, for Meta5.2 GWAnnounced Plan tripled in March 2026 to ten plants and 7.5 GW, with Meta paying about $11B; these seven still need state approval. 5.25 GW is our subtraction. The Lens, 2026-04-03
Renewable power tied to HyperionSolar and batteries, for Meta2.5 GWAnnounced About 2.5 GW reported alongside the gas deal; mix not given. Overlaps 1.5 GW of solar approved in 2025. The Lens, 2026-04-03
Gas generators for Meta El PasoGas plant built for the campus, for Meta0.37 GWAnnounced 813 small gas generators dedicated to the campus for five years, then to the grid; awaiting a state vote. Inside Climate News, 2026-09-24
Clinton nuclear plant for Meta, IllinoisExisting nuclear plant, for Meta1.1 GWAnnounced 20271.12 GW for 20 years from June 2027; keeps an existing plant running, plus a 30 MW upgrade. Constellation Energy, 2025-06-03
Perry and Davis-Besse nuclear plants for Meta, OhioExisting nuclear plant, for Meta2.2 GWAnnounced 20262.18 GW of existing output; Perry from December 2026, Davis-Besse from December 2027. World Nuclear News, 2026-02-27
Upgrades at Vistra nuclear plants for MetaNuclear uprate, for Meta0.43 GWAnnounced 2031433 MW of new capacity, one upgrade a year from 2031 to 2034. American Nuclear Society (Nuclear Newswire), 2026-01-12
TerraPower Natrium reactors for MetaNew reactors, for Metaup to 2.8 GWOption or up to 2035Up to eight units and 2.8 GW; Meta funds two, the rest are rights; first delivery year not set. American Nuclear Society (Nuclear Newswire), 2026-01-12
Oklo reactors for Meta, OhioNew reactors, for Metaup to 1.2 GWOption or up to 2030Up to 1.2 GW, first power as early as 2030; no construction approval yet. American Nuclear Society (Nuclear Newswire), 2026-01-12
NextEra solar and batteries for MetaSolar and batteries, for Meta2.5 GWBeing built 2028About 2.5 GW across 11 contracts and two battery deals, entering service 2026 to 2028, over the grid. Latitude Media, 2025-12-08
Williams 'Socrates' gas plant phase one for Meta, OhioGas turbines on site, for Meta0.2 GWRunning 2026First phase complete (August 2026); output dedicated to Meta's campus and not connected to the grid. Williams (investor release), 2026-08-03 Williams, 2026 Power Engineering, 2025-06
Williams 'Socrates' gas plant phase two for Meta, OhioGas turbines on site, for Meta0.2 GWBeing built late 2026Second phase targeted for the fourth quarter. Williams (investor release), 2026-08-03 Williams, 2026 Power Engineering, 2025-06

Power in gigawatts. Deals sized in gigawatts overlap with sites and are never added to them. See Is there enough power for AI? for the full picture.

Data as of 2026-11-17. Cite as: Ye, Mike. "Meta" (meta). AI Lattice, dataset v0.6.0. https://ailattice.ai/e/meta/. How to cite.