Map / Power
Eaton ETN
Switchgear, power distribution and liquid cooling for data centers.
Chokepoints it holds
Depends on
No sourced links yet.
Supplies
- Nvidia: 800 V DC power design for Nvidia AI factories. Eaton is working with Nvidia on 800-volt direct-current power infrastructure for AI data center racks of 1 MW and beyond. Eaton (Business Wire), 2025-07-15
AI money
Full-year 2025 audited figures; Q2 2026 segment trends. Q3 2026 results not yet out as of Oct 30, 2026.
Where the money comes from
| What | Amount | Period | Detail and source |
|---|---|---|---|
| Cash from its own business | $4.5B | FY2025 | On revenue of $27.448B. Backlog about $19.8B at Dec 31, 2025. Filing credits 'momentum in the data center and utility end markets' without quantifying the data center share. SEC EDGAR, 2026-10-16 |
Where it goes
| What | Amount | Period | Detail and source |
|---|---|---|---|
| Acquisitions to Boyd Thermal | $9.5B | agreed Nov 2, 2025; closing expected Q2 2026 | Data center liquid cooling business. Also bought Fibrebond ($1.43B, Apr 2025) and Ultra PCS ($1.53B, Jan 2026). Closing status of Boyd not confirmed in source read. SEC EDGAR, 2026-10-16 |
| Data centers and equipment | $919M | FY2025 | Property, plant and equipment spending. SEC EDGAR, 2026-10-16 |
Amounts in US dollars. "Up to" amounts are maximums or depend on conditions. See Does it add up? for the full picture.
Data as of 2026-11-17. Cite as: Ye, Mike. "Eaton" (eaton). AI Lattice, dataset v0.6.0. https://ailattice.ai/e/eaton/. How to cite.